Construction Work for the Primary Crushing Leachable Deposits Formation Project at Toquepala
TOQUEPALA - TACNA MINE, Peru
The Leachable Deposits Formation Project is part of the Toquepala mine modernization plan. The primary structure is the Crushing Building, which has the mission of crushing the large volumes of minerals hauled to the building. The Primary Crushing building stands 41 m tall and covers a surface area of 390 m2. The crushing building was divided into two zones: the primary zone includes the main slabs (three total) and is divided into four levels, while the secondary zone includes the auxiliary slabs (four total) and is divided into four levels. The Primary Crusher also included the 41 m high cut-off wall construction with total slurry wall surface area of 1,800 m2. Approximately 7,000 m3 of concrete was poured in the crusher building.